MetroLink is Ireland's largest public transport infrastructure project and a key part of Project Ireland 2040. Connecting Swords, Dublin Airport and the city centre to Charlemont, MetroLink is designed to provide a high-capacity, reliable and sustainable transport network that supports Ireland's transition to a low-carbon future.
Climate action is one of MetroLink's core policy objectives. The project aims to deliver a climate-resilient transport system, minimise whole life carbon emissions, and provide low-carbon journeys powered by renewable energy sources. To achieve this, TII requires a robust Carbon Management Plan (CMP) for the overall programme and for individual work packages throughout design, construction and operation.
MetroLink's carbon management process is aligned with PAS 2080:2023 – Carbon Management in Buildings and Infrastructure, the internationally recognised framework for managing and reducing whole life carbon emissions across infrastructure programmes.
Our approach establishes a structured process to:
Carbon management is embedded across the project lifecycle, ensuring that carbon reduction is considered alongside cost, programme, quality and operational performance.
The MetroLink project supports Ireland's Climate Action Plan and national carbon budgets by:
Early integration of carbon management into design and procurement allows the project team to maximise opportunities for carbon reduction when influence over project outcomes is greatest.
The current project baseline has been derived from the Environmental Impact Assessment Report (EIAR).
Total Estimated Embodied Carbon
1,016,536 tCO₂e
Key Sources of Embodied Carbon
|
Source |
Carbon Emissions (tCO₂e) |
|
Materials |
474,663 |
|
Plant Use |
401,010 |
|
Excavation |
54,345 |
|
Construction Waste Transport |
40,778 |
|
Maintenance Materials |
25,661 |
|
Construction Waste Disposal |
14,907 |
|
Material Transport |
4,634 |
|
Construction Water Use |
494 |
|
Clearance, Demolition & Excavation |
45 |
The baseline will be reviewed and updated as the Reference Design, Tender Design and subsequent Detailed Design progress, providing increasing levels of accuracy and enabling improved carbon reduction monitoring.
Through commitments made during the Railway Order process and Oral Hearing submissions, MetroLink has established a number of key carbon reduction requirements.
Apply PAS 2080 principles throughout design, procurement and construction activities.
Analysis undertaken during the project development process identified the potential to achieve approximately:
51.7% reduction in embodied carbon emissions
when compared with the original embodied carbon estimate through measures including:
The project will update this throughout delivery and development, and targets will be consistently reviewed.
MetroLink follows the PAS 2080 Carbon Reduction Hierarchy:
1. Avoid
Challenge the need for carbon-intensive activities and seek opportunities to eliminate emissions before they occur.
Examples include:
2. Switch
Replace high-carbon solutions with lower-carbon alternatives.
Examples include:
3. Improve
Increase efficiency and maximise value from resources already required.
Examples include:
Throughout the programme, MetroLink will:
Measure
Reduce
Manage
Collaborate
MetroLink's carbon management framework supports compliance with:
The project recognises that compliance with planning approval alone is not sufficient. Carbon management must be demonstrably embedded into project decision-making and delivery to support Ireland's climate objectives.
Carbon management will remain a central component of MetroLink delivery. As design develops and procurement progresses, carbon assessments will be refined, opportunities identified and performance continually monitored against project requirements.
Through collaboration across the programme, MetroLink aims to deliver a transport system that not only improves connectivity across Dublin but also leaves a lasting legacy in sustainable infrastructure, supporting Ireland's journey towards a low-carbon future.